Site Inspections
The regulations require that the person carrying out building
work must give the Council notice when the work has reached a
particular stage. The prescribed stages are set out
below.
The notice may be submitted either:
In Writing to: Building Control, Duke House, Clensmore street,
Kidderminster, Worcestershire, DY10 2JX.
Special postcards that may be used to give the written notice
are supplied free of charge.
By Telephone: 01562 732509
or Online:
Request a Site Inspection
Special postcards that may be used to give the written notice
are supplied free of charge.
The following are the stages at which notification should be given.
Stage 6 is not mandatory but it is strongly recommended.
Click on the description below for additional information.
Stage 1
Commencement
Stage 2 Foundation
Excavated
Stage 3 Foundation
Constructed
Stage 4 Damp Proof
Course
Stage 5 Ground Floor
oversite (before concrete is laid)
Stage 6 Drains
before backfilling
Stage 7 Drains before
backfilling (testing)
Stage 8 Interim
Inspection - Pre-plastering Stage
Stage 9 Occupied
before completion (where applicable)
Stage 10 Work
Completed
Before work commences on site you should inform the Building
Control Service that work is about to begin. It may be necessary or
desirable to have a site meeting at this stage to discuss the
project and work through any possible problems that may not be
apparent from just a check of the plans alone.
2. Foundation Excavation
Once the foundations for the proposed building have been
excavated it is essential that prior to concrete being placed the
Council be invited to inspect the works to date. At this stage
Building Control will consider the depth of excavation in relation
to strata type, location of trees, proximity of drains or wells and
adjacent buildings or basements.
3. Foundation Constructed
After the foundations for your building are concreted an
inspection of the completed Foundations must be made. We will be
looking to ensure that the concrete is of sufficient depth and
quality to allow the safe transfer of load from the new Building to
the Ground.
4. Damp Proof Course
When the Damp Proof Course (D.P.C.) is laid on a solid or cavity
wall it will need to be inspected to ensure that it will fulfill
its function in preventing rising damp in the buildings fabric. In
general a D.P.C. should be positioned 150mm above external ground
level and be linked with all abutting D.P.C.s and the Damp Proof
Membrane (D.P.M.).
5. Over-site Inspection
When the over-site (floor) preparation is ready to pour the
concrete, notice should be given to the Building Control provider,
to enable it to be inspected before the floor slab is cast. The
over-site preparation should include well compacted and blinded
hardcore together with a 1200 gauge damp proof membrane (Or 1000
gauge if to the P.I.F.A standard).
The membrane is usually continuous with the dpc. Variations of the
membrane position may be necessary. e.g. radon proof barrier.
Insulation will usually be required, which may go above or below
the concrete slab. Depending upon the design, steel reinforcement
may also be necessary.
Other forms of ground floor construction will also need to be
inspected before they are covered over.
6. Drains before backfilling
All laid drains be they for Foul or Rainwater must be inspected
before they are covered over. This is to ensure that adequate falls
accessibility and capacity is provided and that the drains are
provided with adequate protection once covered. A test of the
drainage to ensure a watertight system may be undertaken at this
stage and again at the completion stage
7. Drains before backfilling (testing)
When the drainage has been covered a supervised test to ensure a
watertight system should be undertaken and again at the completion
stage.
8. Interim Inspection – Pre-plastering
Stage
Though not a stage of construction requiring statutory
notification, most surveyors will wish to carry out an interim site
visit often referred to as a pre-plaster inspection, or sometimes
simply as a roof inspection. The exact timing of this visit will
vary depending on the nature of the project and the requirements of
the surveyor in question, so it is advisable to check with your
Building Control department to establish when this should
occur.
This can be a valuable opportunity to both review the work that has
been carried out up to that point, perhaps identifying any problems
while they are still relatively easy to rectify, and to discuss the
future works necessary to progress the works through to a
successful completion.
Listed below are some of the areas that may be discussed at this
stage, along with some of the more common pitfalls. This list is
based on a typical new dwelling, and is not exhaustive since no two
projects are the same. It will however give some useful
pointers.
Roof structure: In the case of a prefabricated truss roof, checks
will be made on the verticality and spacing of the trusses, the
quantity and positioning of timber roof bracing and the
installation of metal gable and wall-plate restraint straps.
Manufacturers design calculations will be requested for the trusses
if not already provided. In the case of a traditional cut roof, the
survey will also address the sizes of the timbers used, and the
general workmanship of connections, notches and joints.
The method of providing ventilation to the roof space may be
discussed, which can be achieved through installation of
proprietary eaves ventilators (along with ridge vents if sloping
ceilings are planned), or may be provided through the use of a
vapour permeable roofing felt. In the case of the former, the
relationship between airflow and roof insulation should be
considered. If the latter is proposed, then it must be exactly as
per the manufacturers certified details, which may include
counter-battening or other measures which would not otherwise be
considered necessary.
First floor joists: The size of the joists in relation to the span
will be checked, as will the installation of structural noggins and
wall restraint straps where required. Where they bear onto external
walls, the joists should either be on hangers, or built in via
proprietary sealing units.
Insulation (type and thickness in relation to the required
U-values) may be inspected or discussed at this stage. Insulation
to the roof and to sections of sloping ceiling may already be in
place. In the case of timber frame structures, the insulation and
vapour barrier to external walls may also be viewed prior to
plasterboarding. Remember that walls and floors abutting unheated
spaces (eg. garages and loftspaces) must achieve the same thermal
values as if they were external elements.
For acoustic purposes, some form of insulation may also be required
to the majority of internal floors and hollow partitions. If you
are building more than one attached dwelling, far more rigorous
standards will apply to the separating wall/floor elements, and you
should consult carefully from the start with your Building Control
Department as well as your appointed designer.
Stairs and Balustrades: If the stairs have been installed at this
stage, then checks will be made, to include the following: The
pitch of the stairs (which should be less than 42 degrees), the
size of landings, including any restrictions imposed by doors which
swing onto them, the height of balustrades (generally 900mm to
internal stairs/landings) and the spacing of balusters (no more
than 99mm).
Doors to the Ground Floor: The main entrance door should provide a
clear opening of at least 775mm wide. The minimum width for
internal doors will range from 750mm to 800mm, depending on their
relationship to the hallway or corridor off which they open.
Remember that clear opening widths must allow for the thickness of
the door itself, and so a 750mm door will not provide a clear
opening of 750mm.
Wall sockets and switches should all be mounted within a zone of
450 – 1200mm from the finished floor.
A ground floor WC is required, to a size and layout which complies
with the guidance in Approved Document M, and this will normally be
far enough advanced to verify at this stage. An outward opening
door will almost certainly be a requirement.
Windows and Doors: the glazing specification will be checked to
ensure that it complies thermally (a u-value of 2.0 or under for
timber or plastic windows, or 2.2 for metal windows) and that
safety glass has been used where necessary (within 800mm of the
floor, or 1500mm in the case of glazed doors/glazing to either side
of doors). Windows which are required to provide escape in the
event of a fire may also be checked at this stage to confirm that
they provide a large enough clear opening – a minimum of 0.33M2 and
no less than 450mm in width or height, with the bottom of the
opening falling between 800 and 1100mm of the floor. (escape
windows are required primarily to bedrooms, but can be called for
in other rooms depending on circumstances). Finally, the provision
of background ventilation to all rooms, most commonly achieved
through the inclusion of vents in the heads of the windows, can
also be seen at this point.
Electrical Installation: Electrical works that are not being
installed by a contractor under the government’s ‘competent
persons’ scheme will require inspecting at this stage.
If the installation is being carried out by a contractor under the
‘competent persons’ scheme an inspection at this stage is also a
useful way of checking that the other requirements of the Building
Regulations are being met.
In any case the surveyor will normally remind the contractor at
this stage that a copy of the commissioning certificate will be
required at completion. Failure to provide a suitable certificate
will result in the completion certificate being held back.
Future works often discussed during this visit may include the
following:
Requirements for extract ventilation to kitchens, utility rooms and
bathrooms. Fans provided to windowless rooms should operate with
the light switch, and operate on a timed over-run.
The provision of smoke detectors, which must be mains operated,
inter linked and backed up with a battery. At least one per storey
will be required, but sometimes more depending on the size and
layout of the dwelling.
Proposals for a ramped or level access to the property, leading to
an accessible threshold (with no steps greater than 14mm).
Thickness and type of any insulation still to be installed.
Lengths and diameters of internal waste & sanitary
pipework.
Fire Protection of the Structure – Any structural elements which
form part of, or give support to a floor in a dwelling are required
to be fire resistant for a minimum period of 30 minutes. This may
include walls, steel or timber beams and timber floor joists.
Methods of protection could be by cladding/lining (eg.
plasterboard), applying intumescent paint treatments and, in the
case of some timber structural elements, over-sizing to ensure they
will remain structurally sound for the required period even when
burning. In the case of plasterboard ceiling linings, which tends
to be the most common solution, consider the measures necessary
where penetrations occur to the ceiling (eg. where inset spotlight
fittings are cut into the ceiling).
Fire separation of fire risk areas – most commonly an integral or
attached garage, which must be separated from the dwelling by 30
minute fire-resisting construction complete with self-closing fire
doors if access is to be provided between the garage and the
house.
Position and type of central heating boiler, especially the flue
terminal, in relation to any opening windows, doors or vents. The
provision of ventilation to any open flue appliances (including
open fireplaces and wood burners) may also be discussed. Gas
boilers should be of the condensing variety unless proven to be
unreasonable to be installed.
Positioning, where relevant, of LPG or oil storage tanks. The level
of fire risk to the building or any boundary will be relevant, as
will the possibility of polluting watercourses in the case of oil
tanks.
Paperwork which may be required for completion, eg. outstanding
structural calculations, SAP ratings etc.
9. Occupied before completion (where
applicable)
This inspection is carried out if the new building is to be
occupied before it can be considered complete for the purposes of
the Building Regulations.
10. Work Completed
This inspection is carried out as the name suggests when all work
is completed. Most aspects of the construction are gone over a
second time to ensure the building works are satisfactory. A drains
test for example may be undertaken on any new drainage installed.
If the work is found to be satisfactory and all other relevant
inspections have been made a Completion Certificate for the work
will be issued.
MOST HOUSE SALES WILL REQUIRE A COMPLETION CERTIFICATE FOR ANY
WORKS UNDERTAKEN THAT HAVE REQUIRED BUILDING REGULATIONS
APPROVAL.
In the case of non-domestic work, staged completions may be
required. For example, completion of all works relating to fire
precautions and means of escape.